| |
 |
 |
 |
|
| |
  
|
|
|
|
|
|
|
|
PROJECT EXAMPLES
Whittaker
Creek Campground Water Treatment System |
 |
The Bureau of Land Management (BLM), Eugene District retained our staff to
construct an ultraviolet treatment system, conveyance lines and campground
hydrants for Whittaker Creek Campground. |
|
|
Our staff installed over 3,000 linear feet of 1 1/2-inch diameter schedule
40 PVC pipe. The campground
contains two wells that were fitted with hand pumps used for obtaining
drinking water. As part of
the construction and installation services, one well was fitted with a
submersible pump and piped to the treatment system.
Then treated water was piped throughout the campground.
Materials in contact with water had to have National Sanitation
Foundation (NSF) certification (NSF 61) for potable water use.
In addition, the wellhead piping, fittings, and conveyance lines
installation was consistent with standards of practice as specified by the
American Water Works Association (AWWA).
|

|
 |
The treatment system was installed in a pre-fabricated concrete building.
The treatment system consisted of an ultraviolet (UV) disinfection
unit capable of treating up to 9 gallon-per minute from the well.
In addition to the treatment system installation, seven
self-closing hydrants were constructed around the campground, as well as
an ADA compliant drinking fountain.
|
|
Other construction activities included a bridge crossing of water and
electrical lines. The
campground is split by Whittaker Creek and required a waterline crossing
on a footbridge to accommodate both sides of the campground. |

|
|
. |
|
Commercial
Property Phase I ESA |
|
Advanced Remediation Technologies, Co. was
retained as a consultant to perform numerous Phase I environmental site
assessments of properties of interest (i.e. agricultural and retail) to
evaluate whether potential environmental issues may impact the subject
properties. The Phase I’s
were conducted according to the American Society for Testing and Materials
(ASTM) Phase I standard practice (Doc. E 1527-00).
The Phase I’s were used by the Client to make decisions on
property transfers. The
purpose of the Phase I is to identify “recognized environmental
conditions” in connection with a site.
Recognized environmental conditions are defined as the presence, or
likely presence, of hazardous substances or petroleum products on the site
that could indicate an existing release, a past release, or a material
threat of a release of hazardous substances or petroleum products into
property structures, surface water, ground, or groundwater.
|

|
|
For our clients the purpose of a phase I
environmental site assessment (ESA) is to satisfy one of the requirements
to qualify for the innocent landowner defense to the Comprehensive
Environmental Response, Compensation and Liability Act (CERCLA) liability,
as defined in 42 USC 9601(35)(B). ARTs
numerous Phase I ESAs for commercial properties that typically included: |
- Records Review
– Review of local, state and federal agency records
(including building permits, environmental data bases, historical fire
insurance maps, land title records, aerial photographs etc).
- Site Inspection
— A visit to the site to
obtain information indicating the likelihood of recognizable
environmental conditions (including existing site uses, adjacent site
uses, above/below ground storage tanks, water wells, dry wells,
chemical storage area, solid waste disposal, etc.)
ART observed and report the presence of visually apparent
suspect asbestos materials (SACM), including the extent and current
conditions of any visually apparent SACM.
- Interviews— Interviewed with current owners
and occupants of the subject properties, as well as local regulatory
officials
- Evaluation and Report—The reports contained baseline information on the
sites, document the findings of the Phase I ESA activities, and
conclusions and recommendations of appropriate follow-up activities
(as necessary) to evaluate whether potential environmental concerns
are present.
|
|
|
|
Municipal
Water Supply Treatment |
 |
The Arizona Department of Environmental Quality (ADEQ)
retained our staff to evaluate and select a groundwater treatment
technology and design and construct the selected treatment system for a
contaminated municipal well field. Contaminants
of concern included the chlorinated solvents terachloroethylene (PCE),
trichloroethylene (TCE), 1,2-dichloroethane (1,2-DCA), and
cis-1,2-dichloroethene (cis-1,2-DCE) which came from a defunct dry
cleaners that disposed of spent cleaner solvents into a dry well.
The affected wells were installed by the Town of Payson to meet a
projected water shortage, but the well water was found to be contaminated
and could not be used without treatment. |
|
The project was funded by the Arizona Water
Quality Revolving Fund (WQARF) that provides money for site cleanup.
The Payson WQARF site was one of the first major cleanups to be
conducted under the program and served as a model for future sites.
This was also the first design/build project of a treatment system
for the ADEQ. |

|
|
|
Our staff evaluated alternative treatment
technologies for treatment efficiency, compatibility with drinking water
treatment, operations and maintenance requirements, and life-cycle cost.
Carbon adsorption was selected as the treatment method because it
is proven and reliable and was less expensive than acceptable
alternatives. Groundwater
flow was modeled to assess contaminant capture and estimate groundwater
extraction rates. The
state-of-the-art system was designed to treat flows up to 1,300 gallons
per minute at in influent PCE concentration of 2,000 μg/.
|
|
Our staff worked closely with ADEQ to define project requirements, to
develop the technical scope, and construct and install the system.
Our staff also responded to the needs of the Town of Payson to
ensure that the requirements for the public water supply were met,
including demand scheduling, operational requirements, and public
relations. Because of projected water shortages in the Town of Payson a
rapid schedule was placed on the project.
Our staff completed technology evaluation to having a system
on-line within 10 months. The
treatment system was designed to be turn over to the town to operate. Therefore, the treatment system was designed to provide
reliable operation with minimal operator commitment.
System functions, including groundwater extraction, groundwater
conveyance, system monitoring, alarm functions, and data management were
controlled by a programmable logic controller (PLC) configured for remote
system monitoring and operation through a human machine interface (HMI)
with a dedicated on-site personal computer. |
|
|
Groundwater extraction pumps were controlled by variable frequency drive (VFD)
controllers that allowed precise control of drawdown and well production.
Treated groundwater is chlorinated with a sodium hypochlorite
inline injection system as it is pumped to an on-site welded steel 100,000
gallons storage tanks. The
treated and disinfected water is added to the distribution system through
a duplex pump system that is flow controlled through a VFD.
The conveyance piping for the all extraction wells was constructed
of high density polyethylene SDR 11 NSF 61 certified pipe that was both
butt fused and electro-fused for a zero leakage conveyance network.
The system has had a 99-percent runtime with only downtime due to
pre-filter and granular activated carbon change out. |
|
.
|
|
Former
Automotive Dealership
|
|
ART was retained as a consultant for completing
the cleanup of petroleum hydrocarbons from the leaking UST.
Several shallow groundwater contaminant plumes with different sources
appear to be present on the site and adjacent properties.
The on-site groundwater contamination is dominated by the LNAPL
originating near the lube oil rack in the building and the gasoline UST,
which reportedly was abandoned in-place some years ago.
Most of the LNAPL-associated groundwater contamination is present
below the service bays of the existing building.
The off-site shallow groundwater contamination appears to be
originating from offsite, possibly on the adjacent property.
The off-site sources of groundwater contamination resulted in
relatively low concentrations of chlorinated compounds migrating onto the
I&O site.
|
|
Groundwater contaminant concentrations on the
I&O site ranged from not detected (ND) to three feet of LNAPL.
Analysis of the LNAPL determined it consisted mostly of heavy oils
with smaller amounts of gasoline, petroleum-related VOCs, chlorinated VOCs,
and polycyclic aromatic hydrocarbon (PAH) compounds (LNAPL constituents and
characteristics are discussed in greater detail in the next memo section).
The product analysis correlated to two likely nearby sources, the
lube oil rack and the gasoline UST, and not to the waste oil UST that was
decommissioned.
With DEQ oversight since 1999, ART on behalf of
Immer and Oswald have completed the site characterization requirements,
submitted the data, and proposed and obtained “No Further Action” on the
site contingent with on site use restrictions limiting access to the LNAPL
plume on site.
|
|
|
.
|
|
LUST
Remediation
|
|
Advanced Remediation Technologies, Co. was
retained as a consultant and remediation contractor for completing the
cleanup of petroleum hydrocarbons from leaking underground storage tanks (LUSTs).
The LUSTs had been removed prior to our involvement.
Additionally, contaminated soils surrounding the leaking LUSTs was
removed during decommissioning. Our
company was asked to take over the project when contamination was discovered
to have migrated beneath the foundation of the buildings on site.
Our staff evaluated alternatives for treatment.
The site soils are fine-grained in the vadose and saturated zones,
but appeared permeable enough for soil vapor extraction (SVE) to be
effective treatment mechanism. The
major contaminants of concern consisted of benzene, toluene, ethyl benzene,
and total xylenes (BTEX) and total petroleum hydrocarbons.
|
|
The SVE system was design and installed with the
extraction wells and trench galleries located in the building.
The equipment was located outside for noise and ease of operation and
maintenance. Advanced
Remediation Technologies installed the system and has provided operation and
maintenance support since the system was started.
In the first 2 months of operation, the benzene contaminant level was
reduced from 153 mg/m3 to non detect.
Advanced Remediation Technologies not only has come in under budget
for this project but also has saved the client money by providing full
services. Additional services provided by ART were preparation of
conceptual site model, groundwater monitoring, and risk-based closure
evaluation. Currently, the site
is under the final steps (public comment) for obtaining “No Further
Action” with limited deed restrictions with the DEQ.
|
|
|
.
|
|
©2004-2008
All Rights Reserved |
|